Home / ADU / Florida ADU rules

ADU rules in Florida

Representative cities: Miami, Orlando, Tampa.

Verify locally. Florida uses the statewide Florida Building Code (8th Ed., 2023), but Miami-Dade and Broward are the High-Velocity Hurricane Zone with stricter product-approval and impact-resistance rules. Local fees and zoning vary. ADU rules below are drawn from official sources — always confirm with the issuing building department before designing or building.

ADU permit rule

Permit requiredRestrictedcity authority
Fee basis
Permit and plan-review fees set by the city. Verify with the local building department.
Typical timeline
Varies by city; 2–8 weeks.
Setback
Per local zoning.
Area threshold
Allowed where local zoning permits (e.g., Miami 21, Orlando, Tampa).
Exempt if
None — where allowed, ADUs require a permit.
Go / no-go
restricted
Florida has no statewide by-right ADU mandate; ADUs are allowed only where the local ordinance permits, with size/setback set by that ordinance.

Frequently asked questions

Do I need a permit to build an ADU in Florida?

Per Florida rules, an ADU is "yes" for a permit and the authority is "city". Florida has no statewide by-right ADU mandate; ADUs are allowed only where the local ordinance permits, with size/setback set by that ordinance. Always confirm with the issuing building department.

How big can an ADU be in Florida?

Area threshold: Allowed where local zoning permits (e.g., Miami 21, Orlando, Tampa).

What are the ADU setbacks in Florida?

Setback: Per local zoning.

How much does an ADU permit cost in Florida?

Fee basis: Permit and plan-review fees set by the city. Verify with the local building department.